Is there any way to stop OmniPlan from dividing tasks.
As an example, I have my task list created, and have a group of two resources called Developers (with two resources inside Fred and John). Fred works 80% of the time on this project, John can spare 20% of his time. Tasks are all assigned to the "Developers" group.
If I now level the project, all tasks assigned to Developers will be split - 80% of each task will be assigned to Fred and 20% to John, but their task list will be exactly the same. I would like that about 80% of the tasks would go to Fred and 20% of the tasks would go to John. I do not want my tasks to be split between people as I already have broken each task down into its own distinct work package.
Am I missing something here to fix this?
As an example, I have my task list created, and have a group of two resources called Developers (with two resources inside Fred and John). Fred works 80% of the time on this project, John can spare 20% of his time. Tasks are all assigned to the "Developers" group.
If I now level the project, all tasks assigned to Developers will be split - 80% of each task will be assigned to Fred and 20% to John, but their task list will be exactly the same. I would like that about 80% of the tasks would go to Fred and 20% of the tasks would go to John. I do not want my tasks to be split between people as I already have broken each task down into its own distinct work package.
Am I missing something here to fix this?