Dear all,

I downloaded the trial version of OmniPlan, and I've created a new Gantt. I am new to this, so please forgive this possibly stupid question!

I think about times as if only one person should do every single task. Then, I add resources, in my case just persons.

So, is it possible to assign people to each task, and have OmniPlan recalculate the needed time?

For example, if I have two persons, and they have to perform a single task that takes two weeks, can I say "assign Jack and Jane to Task 1", and in the resource allocation say "Jack 60% and Jane 40%"?

Again, I may be asking a trivial question, or even an impossible one... So thanks anyway! :)

Cheers!
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Calculated dates jbh OmniFocus 1 for Mac 1 2012-10-08 08:55 AM
Trying to do something basic villageboy OmniGraffle General 3 2011-01-17 04:02 PM
Really Basic, but I need to ask defilmj OmniFocus 1 for Mac 22 2008-12-15 06:36 AM
very basic help scottnh OmniFocus Syncing 6 2008-10-16 11:33 PM
Calculated Estimated Time on Projects bjabernethy OmniFocus 1 for Mac 2 2007-05-23 07:13 PM


All times are GMT -8. The time now is 09:28 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.