Dear all,
I downloaded the trial version of OmniPlan, and I've created a new Gantt. I am new to this, so please forgive this possibly stupid question!
I think about times as if only one person should do every single task. Then, I add resources, in my case just persons.
So, is it possible to assign people to each task, and have OmniPlan recalculate the needed time?
For example, if I have two persons, and they have to perform a single task that takes two weeks, can I say "assign Jack and Jane to Task 1", and in the resource allocation say "Jack 60% and Jane 40%"?
Again, I may be asking a trivial question, or even an impossible one... So thanks anyway! :)
Cheers!
I downloaded the trial version of OmniPlan, and I've created a new Gantt. I am new to this, so please forgive this possibly stupid question!
I think about times as if only one person should do every single task. Then, I add resources, in my case just persons.
So, is it possible to assign people to each task, and have OmniPlan recalculate the needed time?
For example, if I have two persons, and they have to perform a single task that takes two weeks, can I say "assign Jack and Jane to Task 1", and in the resource allocation say "Jack 60% and Jane 40%"?
Again, I may be asking a trivial question, or even an impossible one... So thanks anyway! :)
Cheers!