Good day-
I've looked at a few different types of these programs and am needing something to schedule out our design projects. I have gone through the videos and downloaded the trial, but I am not sure how to account for some aspects of the work that we do.
Most of these programs seem to assume that a single task is going to be done from start to finish in a single session- so a 6 hour task will be about 3/4 of a day, or a 14 hour task is 1 day and 6 hours- all continuous- in other words, the program assumes that you are doing nothing else for that time period.
The reality of our small office means, however, that I am RARELY working on a single task from start to finish. a 6 hour task might get interrupted, or I may have another client meeting for another project in the middle of that task that takes 2 hours, then I go back to the task I started earlier.
So, while a task may take multiple days to complete, that ACTUAL number of hours may be less than the 8 hour day- but there is still office work being done.
One thought may be to "break the task into smaller items"- but that really isn't an option for the work we do- some of these task just take several hours to complete. I could break the task into multiple, adjacent and identical tasks of different times maybe.
I supposed I could go in and manipulate the work work to show only the hours I worked on the project, but that seems overly- complicated.
I wanted to see if this concept had been thought through. Or perhaps there is some other sort of program that I need to be looking at to handle this? Surely this concept has been addressed before now?
Thanks in advance!
I've looked at a few different types of these programs and am needing something to schedule out our design projects. I have gone through the videos and downloaded the trial, but I am not sure how to account for some aspects of the work that we do.
Most of these programs seem to assume that a single task is going to be done from start to finish in a single session- so a 6 hour task will be about 3/4 of a day, or a 14 hour task is 1 day and 6 hours- all continuous- in other words, the program assumes that you are doing nothing else for that time period.
The reality of our small office means, however, that I am RARELY working on a single task from start to finish. a 6 hour task might get interrupted, or I may have another client meeting for another project in the middle of that task that takes 2 hours, then I go back to the task I started earlier.
So, while a task may take multiple days to complete, that ACTUAL number of hours may be less than the 8 hour day- but there is still office work being done.
One thought may be to "break the task into smaller items"- but that really isn't an option for the work we do- some of these task just take several hours to complete. I could break the task into multiple, adjacent and identical tasks of different times maybe.
I supposed I could go in and manipulate the work work to show only the hours I worked on the project, but that seems overly- complicated.
I wanted to see if this concept had been thought through. Or perhaps there is some other sort of program that I need to be looking at to handle this? Surely this concept has been addressed before now?
Thanks in advance!