The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Generic weeks vs. specific dates Thread Tools Search this Thread Display Modes
How do you set OmniPlan to use a generic calendar instead of specific calendar dates? I don't know the start date for a project (it will start whenever it's approved), so I want to show "week 1," "week 2," etc. Is there a way to set this? I couldn't find it, and I'd appreciate a pointer. I'm running version 1.7, if that makes a difference.

Thanks!
Emma
 
Bring up the Project: Information inspector with Inspectors->Project (or command-4). Click on the little suitcase icon to get the Project: Information panel and click the radio button next to Start: Undetermined Date as seen in the attached image.
Attached Thumbnails
Click image for larger version

Name:	Screen shot 2012-02-16 at 5.37.27 PM.png
Views:	675
Size:	22.9 KB
ID:	2264  
 
Thanks! That was exactly what I needed.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
iCal Publishing and Due Dates > 2 Weeks Away joncgde2 OmniFocus 1 for Mac 5 2011-10-23 08:40 PM
How to create a swimlane diagram that is not linked to specific dates? skippingrock OmniPlan General 0 2011-04-01 11:29 AM
Ability to show time in "in three weeks, in two weeks, tomorrow" formats mr_projects OmniPlan General 1 2007-11-02 11:28 AM


All times are GMT -8. The time now is 08:53 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.