Including weekends in the project? Thread Tools Search this Thread Display Modes
Some of my project include weekends, and so I need to have these be included in start and end dates. Yet, OmniPlan does not seem to accept these, and keeps reverting to the closest week day.

Is there a way to deal with it? A setting to change? Anything else?

Thanks,
Simon
 
You need to change the working hours for either the whole project or the specific resources who do work on weekends (as appropriate). This is available in the calendar view. Choose "Calendar View" from the View menu. Then resize the green bubbles to include weekends, or add new green bubbles.
If only some of your resources work on weekends, you can change their specific normal work weeks. If no one normally works on weekends, but there's one weekend where stuff is getting done, you'll want to change the work schedule instead of the normal work week (see drop-down in lower left corner).
You may also find it helpful to turn on "Show Off-hours" (in the View > Gantt Chart menu).
Hope that covers it. If you've still got questions, post 'em here and I'll try again.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
where are the weekends? OmarKN OmniPlan General 4 2012-10-10 09:31 AM
Highlight Weekends noisebug OmniPlan General 1 2010-03-31 05:39 PM
Changing Weekends lspitzner OmniPlan General 2 2009-08-25 10:00 AM
Can not show weekends..? niels.henrik OmniPlan General 8 2008-03-10 05:00 PM
Work on weekends Fake OmniPlan General 2 2006-08-08 12:54 AM


All times are GMT -8. The time now is 11:36 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.