Adding resources makes task take longer? Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I have a task that I assigned 3 days as the effort needed. Then, as I assign resources to this task, it takes longer and longer to complete. With two people working 70% I have 1w 2.75 hrs.

What kinda' of things could I be doing wrong to make it behave like this?

Many thanks in advance.

-jim lee
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
One task, two resources, different hours Bridgeblox OmniPlan General 8 2013-03-15 02:57 PM
Adding multiple resources to a task without changing duration blaketime OmniPlan General 5 2011-10-04 11:57 AM
How About Adding Time Zone Specification for Resources? FrustyCronch OmniPlan General 3 2009-11-17 02:20 PM
2 resources on the same task edasque OmniPlan General 1 2006-08-03 12:46 PM


All times are GMT -8. The time now is 02:18 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.