I have 2 resources. 1 is a staff member available 9 to 5pm the other is a computer available all the time. I then have a task which needs to be performed by this staff member on this computer. Omni plan assigns the work to happen overnight but the staff member is not available at that time. how do I assign a task to happen only when both resources are available?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Quick way to insert new task between dependent tasks? joshfree OmniPlan General 6 2012-07-03 04:25 AM
Automatically Shifting Dependent Tasks? Aldaron OmniPlan General 7 2010-09-21 11:00 AM
Dependent Tasks Haynes OmniFocus 1 for Mac 6 2010-03-13 02:01 AM
Overlap with dependent tasks iangall OmniPlan General 2 2009-09-17 04:51 PM
Request for "dependent tasks" Shanana OmniFocus 1 for Mac 6 2007-08-20 01:39 AM


All times are GMT -8. The time now is 10:57 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.