The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan for iPad
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Calendar Exceptions - how to use? Thread Tools Search this Thread Display Modes
Hi,

I've created a task, assigned to resource 'X'. In resource 'X's profile I've entered an exception in their calendar for two weeks since they're on vacation. This exception time happens during the created task.

I would have expected this to cause the task to extend by two weeks and mark the vacation period on the plan - but instead, it just marks the task as having a violation due to the exception.

Am I doing this wrong? I just want to be able to factor vacation times into my plans and this does seem to be the right approach but it just doesn't do what I would expect...

Thanks,

Jamie.
 
No one?

Is there an official support channel for this product at all? Could really use some help!

Jamie
 
Sorry about this! We spend as much time on the forums as we're able, Jamie, but only after we've taken care of our other duties. In a week when Apple ships a new version of OS X, those duties keep us pretty busy.

In cases where you need a rapid response (and it sounds like this is one), you'll want to send support mail or call 800.315.6664 to reach us by phone. To request support via email, tap the Gear button in the toolbar of OmniPlan for iPad's document picker screen, or send a message to omniplan-ipad@omnigroup.com from your preferred mail app.

Based on your description, I'd expect OmniPlan to do approximately what you're after. It should be extend the duration of tasks overlapping with that vacation, in other words. Can you use one of the methods I mentioned above to get in touch with us so we can investigate this with you? I suspect there's an additional factor of some sort that's causing the exception you're getting; it'll be easiest to figure this out via one of those methods. Hope this helps.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
A lot of exceptions being thrown in my logs krunk OmniFocus 1 for Mac 1 2010-02-27 04:02 PM
Remove Schedule Exceptions lsamberg OmniPlan General 3 2009-10-30 02:57 AM
Assertion exceptions tslarkin Omni Frameworks 1 2009-03-23 08:18 AM
Exceptions and Overtime??? hoju OmniPlan General 1 2008-01-24 11:30 AM


All times are GMT -8. The time now is 06:21 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.