I'm working on a plan that has some external time constraints, and I wanted to represent those as milestones and groups of milestones. One of the goals is to complete the project before the last milestone.
Is it possible to set the critical path so that it omits those time constraints? Right now, the latest date in my plan is a milestone out past the end of all the other items, and as a result, it's a one-item critical path.
I can view the real critical path by deleting the external time constraint tasks, but I wonder if there's another way to handle it.
Thanks in advance,
Scott