1 week is 5 days? What if it's 7? Thread Tools Search this Thread Display Modes
Hi,

I have a team working 7 days a week. I start a new project. It has one default task. I set it's duration to 1 w. I go to calendar view. I set the project calendar to 7 days active. I switch back to Gannt. The task now says 1 w for duration but shows as only five days on the Gannt chart. I have to set it to 1w 2d to have it show a line spanning 7 days on the Gannt chart.

Any help appreciated.

Thanks // :)
 
Bring up the Project : Formatting inspector. Adjust the effort conversion factors to match your needs. Also see this thread: http://forums.omnigroup.com/showthread.php?t=10949
 
Thanks // :)
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Weekly Repeating Project with Tasks on Specific Week Days ttorres OmniFocus 1 for Mac 2 2012-09-02 10:36 PM
Working 7 days per week Allrad OmniPlan General 1 2010-05-24 03:59 PM
hours per day? days per week? fudster OmniFocus 1 for Mac 5 2007-12-19 04:45 AM
"Work Day Hours" and "Work Week Days" in General Preferences dhm2006 OmniFocus 1 for Mac 2 2007-09-05 01:50 PM


All times are GMT -8. The time now is 04:42 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.