I'm trying to manage my team's roadmap with OmniPlan.
Each guy of my team as two types of tasks in a week :
> first are "project tasks" : tasks that belong to a project ;
> second are "everyday tasks" : tasks you have to do every weeks, beside to project tasks.
My question is : how do I set everyday tasks so that it represents 20% of week time, wich means I have 80% of week time for project tasks.
With this setting, a project tasks which duration is 3 days should then be displayed on four days (if a day is 8 hours of work).
Thanks for your help,
Nikozy
I'm trying to manage my team's roadmap with OmniPlan.
Each guy of my team as two types of tasks in a week :
> first are "project tasks" : tasks that belong to a project ;
> second are "everyday tasks" : tasks you have to do every weeks, beside to project tasks.
My question is : how do I set everyday tasks so that it represents 20% of week time, wich means I have 80% of week time for project tasks.
With this setting, a project tasks which duration is 3 days should then be displayed on four days (if a day is 8 hours of work).
Thanks for your help,
Nikozy