Hi all,

I'm currently evaluating OmniPlan and cannot seem to find out if I can do the following. When we map our projects we often do not have a start date for the proposal, so we plan from month 1 to month 36 for a 3 year project (for example). Is there a way I can get the header to do this on the task view?

Thanks,
Chris Power
 
Yes. In the project information inspector, you can change the Start from "On 5/29/08" (or whatever date it's set to) to "Undetermined Start Date". Then the task view will display the kind of labels you want.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Trial Period - Cumulative or Calendar Based? [A: expires 14 days after 1st launch; we can reset it.] Tandem OmniOutliner 3 for Mac 2 2012-08-02 12:28 AM
Changing date from month/day/year to day/month/year RickM OmniPlan General 2 2009-01-27 09:06 AM
Month header in Quarter view? tbrekken OmniPlan General 2 2007-12-06 08:33 AM
Cumulative Days in Gantt Chart danielgjohnston OmniPlan General 3 2007-08-21 02:29 PM
Cumulative project costs tgmclean OmniPlan General 1 2007-05-14 02:44 PM


All times are GMT -8. The time now is 04:21 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.