Is there a way to only show the task efforts as hours?

Right now, it would appear the effort and duration automatically converts to days and weeks, but for a project I have an interested in only displaying the effort as hours.

Is this possible?
 
You can customize what units are used for effort and duration, but you have to use the same units for both. The options are on the Project: Formatting inspector.
 
That took care of it.

Thanks!
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Off Hours bogeninc OmniPlan General 0 2011-11-10 08:05 AM
View "Total Hours" in units of "hours" pheller OmniPlan General 4 2009-11-17 01:37 PM
Display hours next to task in resource view? paulwelty OmniPlan General 1 2007-10-19 11:08 AM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM