Hello
I'm exploring the OmniPlan demo prior to a possible purchase and I appear to have run into something that makes it difficult to use.
I am scheduling a demo video production. Doing this, I would for example have a cameraman assigned to one task over three days 'Shoot'.
To that task, I would assign a meal allocation, say fifty dollars a day.
The way I am doing this is to create a Material Resource 'Meal', with a cost of 50 dollars cost/use, and assign it to the three days 'Shoot' task. I set the Assigned Amount to 3.
Which I would expect to happen in the Resource Inspector is that the total uses (3) is multiplied by the cost/use (50) and a total cost of 150 dollars is reflected.
What I see, however, is a total cost of 50 dollars.
Is this broken, or am I doing something silly?
Many thanks.
I'm exploring the OmniPlan demo prior to a possible purchase and I appear to have run into something that makes it difficult to use.
I am scheduling a demo video production. Doing this, I would for example have a cameraman assigned to one task over three days 'Shoot'.
To that task, I would assign a meal allocation, say fifty dollars a day.
The way I am doing this is to create a Material Resource 'Meal', with a cost of 50 dollars cost/use, and assign it to the three days 'Shoot' task. I set the Assigned Amount to 3.
Which I would expect to happen in the Resource Inspector is that the total uses (3) is multiplied by the cost/use (50) and a total cost of 150 dollars is reflected.
What I see, however, is a total cost of 50 dollars.
Is this broken, or am I doing something silly?
Many thanks.