I started a new project and broke out my tasks,
in looking at the column for effort and the other for duration they do not match.

since I have an 7hour working day with a task that is 7h in effort - should not the duration also equal 1 day rather than 1d 4 h?

Thanks
 
You'll have to give us more information. Do you have resources assigned to the task? Are they assigned at 100%? What is the efficiency for the resources assigned?
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Decouple Effort and Duration? highcamp OmniPlan General 35 2013-03-15 05:13 PM
unlinking effort & duration thormar OmniPlan General 3 2011-07-29 04:07 PM
Different units for duration and effort? LJRolf OmniPlan General 3 2011-02-07 11:39 AM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 05:50 PM


All times are GMT -8. The time now is 08:35 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.