How to Assign Resources "up to" X %?? Thread Tools Search this Thread Display Modes
Hey guys found my self with the same problem as this user has it been solved?

"Example: Four concurrent tasks, one resource

Task 1: 10 hours (effort)
Task 2: 10 hours
Task 3: 10 hours
Task 4: 50 hours

25% of 100% of the resource assigned to each task

Good thing: When leveling resources, OmniPlan (correctly) has the resource start all four tasks immediately.

Good thing: Tasks 1, 2, and 3 finish up in one week (25% of my 40 hour employee to each task).

Bad thing: Task 4 continues to receive only 25% of the resource's time, even AFTER the other tasks are complete (he's underutilized). As a result, it says the task will take 5 weeks (25% = 10 hrs x 5 weeks). In "the real world", he'd spend the entire second week (40 hours) on the last task, and get it done in a week.

Bad thing: If I change the allocation for task 4 to "100% of 100%", it doesn't even let my resource start until he has 100% availability (even though he could, "in the real world", use 25% of his time on it in week one.

Bad thing: I can't micromanage this - with changing dates and priorities, I don't know "which date" to bump my resource's allocation on - I'd (preferably) want Omni focus to do it for me.

So how do I tell Omnifocus "This task requires a minimum of 25% of this guy's time - don't schedule this task until he has that availability. BUT, if he has MORE than 25% availability, use it all, up to 100%"?

What am I doing wrong? Can this be done?

(new to the forum - thank you for the help - would appreciate any helpful links/resources on the subject - apologies if a repeat question - and sorry for the rambling!) ;)"

Thanks in advance!
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can't assign to "all desktops" travisp OmniFocus 1 for Mac 0 2013-05-07 06:15 AM
Group Name for Tasks in "Resources" View Mode Promo OmniPlan General 3 2012-04-21 01:21 PM
How to Assign Resources "up to" X %?? zbacon OmniPlan General 7 2012-03-27 04:19 PM
canīt assign a project to an action in "context mode" levy OmniFocus 1 for Mac 5 2008-01-07 12:59 PM
stop loading resources in "network activity" andreas_g OmniWeb Feature Requests 0 2007-04-11 09:05 AM


All times are GMT -8. The time now is 12:46 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.