Hello,
I have been trying out the demo of Omni-Plan and the UI and documentation is SO FAR ahead of Merlin or Fast Track, it's amazing. That being said, I have a list of questions for you which (hopefully) you can easily answer:
* Is there a way to flip-flop priorities so Priority 1 is top (as all our other software)? Alternately, just have priority be "Very High, High, Normal, Low, Very Low". That's so clear... and I don't have to worry about one PM thinking one way, and another doing it backwards.
* Can you view resources in terms of WEEKS instead of DAYS? Since we don't know if a client will get us materials on Monday or Tuesday, we care mostly about utilization on a weekly basis, not daily.
* Can the color coding of resources have some variance? For instance instead of Green being “EXACTLY” full, could green be full +- 15%?
Undo appears not to work after leveling
* Is there a way to import “time worked on task, by resource” from another system automatically?
* Is there a way to flag milestones as “internal”, and print a “client only” schedule, with only key milestones? I've seen this called "private" with a checkbox before.
Thanks in advance for any help,
Jason
www.gravityswitch.com
I have been trying out the demo of Omni-Plan and the UI and documentation is SO FAR ahead of Merlin or Fast Track, it's amazing. That being said, I have a list of questions for you which (hopefully) you can easily answer:
* Is there a way to flip-flop priorities so Priority 1 is top (as all our other software)? Alternately, just have priority be "Very High, High, Normal, Low, Very Low". That's so clear... and I don't have to worry about one PM thinking one way, and another doing it backwards.
* Can you view resources in terms of WEEKS instead of DAYS? Since we don't know if a client will get us materials on Monday or Tuesday, we care mostly about utilization on a weekly basis, not daily.
* Can the color coding of resources have some variance? For instance instead of Green being “EXACTLY” full, could green be full +- 15%?
Undo appears not to work after leveling
* Is there a way to import “time worked on task, by resource” from another system automatically?
* Is there a way to flag milestones as “internal”, and print a “client only” schedule, with only key milestones? I've seen this called "private" with a checkbox before.
Thanks in advance for any help,
Jason