Can't change date for task started before today? [A: Remove constraint in Task:Schedule inspector] Thread Tools Search this Thread Display Modes
I would like to back date a project, because I have a project already in flight that I want to bring under Omni Plan control.

I have tried removing the start constraint on all tasks, tried adjusting the project start date, and have tried marking everything as complete. However none of these solutions seem to work.

Looking for an override here.

thanks to all. Great application, by the way.
 
I have found that you also need to remove the constraint from all parent Group tasks for this to work. That wasn't obvious to me when I was working on this problem.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
New task without any schedule Maxi OmniPlan General 0 2011-04-15 06:06 AM
Define constraint as a function of another task? juliabell OmniPlan General 1 2009-09-12 09:30 PM
How to see only task groups that have started? [A: See thread.] jaydcowan OmniFocus 1 for Mac 2 2009-08-06 07:17 PM
Daily task not done today, how do I remove it... iangall OmniFocus 1 for Mac 7 2008-12-03 03:18 AM
Dependency/constraint: End before task tlester OmniPlan General 1 2008-09-05 01:34 PM


All times are GMT -8. The time now is 03:15 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.