The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Total cost on task bars in GANT view Thread Tools Search this Thread Display Modes
Hi, preparing a GANT layout of a project for a customer. It would be nice to have costs at the right end of each task bar in the GANT scheme, how?
 
Go to the View menu and select the menu item 'View Options'. Edit the task labels so that "Total Task Cost" is in view to the left or right of the appropriate Gnatt item.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
One task, three resources, how do I get an accurate total cost? jimantonopoulos OmniPlan General 1 2011-04-18 11:49 AM
Unable to drag task bars in Gantt view jtwms1 OmniPlan General 8 2010-12-26 10:04 AM
Task name in gant view chefcrsh OmniPlan General 5 2009-07-02 09:12 AM
Total Cost blank if assign task to resource group. gregc OmniPlan General 2 2007-02-06 12:15 PM
Showing total resource cost for task groups? docswab OmniPlan General 4 2007-01-04 05:03 PM


All times are GMT -8. The time now is 01:46 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.