Discontinuous tasks Thread Tools Search this Thread Display Modes
Hi, I'm going to be reviewing OmniPlan for the first time, and have a question. I've used other PM software for construction projects and have often been frustrated by not being able to break up a task into non-continuous segments without making a new task for it. For example, one task may be slotted in for 3 weeks in the planning stage but in reality the subtrades show up for a week, then don't come back for 1 1/2 weeks, then come back for a week, and then work 4 days, etc. I need to be able to adjust the planned task to reflect the actual periods when it was executed. Can OmniPlan accommodate this easily?
 
Quote:
Originally Posted by archeus View Post
Hi, I'm going to be reviewing OmniPlan for the first time, and have a question. I've used other PM software for construction projects and have often been frustrated by not being able to break up a task into non-continuous segments without making a new task for it. For example, one task may be slotted in for 3 weeks in the planning stage but in reality the subtrades show up for a week, then don't come back for 1 1/2 weeks, then come back for a week, and then work 4 days, etc. I need to be able to adjust the planned task to reflect the actual periods when it was executed. Can OmniPlan accommodate this easily?
There isn't a way to split the task that way in OmniPlan right now. The only workaround would be to create two tasks for Task A and call them "part 1" and "part 2". Not a very elegant solution I know.

We have a feature request for split tasks in our database so I'll add a vote to it for you. :)
 
Thanks. This would be really useful for real-world situations particularly construction. I've made do in other programs by splitting up the task as you suggest but on a large project it takes too much time to manage. entering the time exactly as it occurs in the original task would really help.
 
Yeah I just wanted to add another vote for split-task functionality. I found this to be a really useful feature in MS Project so it would definitely be good if this existed in OmniPlan.

Thanks!
 
Please add another vote for me. I would really like to ditch M$ Project.
 
Votes added. Thanks!
 
Add another!
Thanks
 
And another, please. This is one of the few things that is keeping me -- unhappily -- in Project.
 
Add another vote please
 
Please add my vote
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
repeating projects/tasks when all tasks/subtasks are complete? djc225 OmniFocus 1 for Mac 1 2012-03-20 06:55 PM
Mirroring tasks/Changing color of flagged tasks OmniFocused OmniFocus 1 for Mac 3 2011-09-21 04:20 PM
Adding tasks in inbox on iPad deletes other tasks kocab OmniFocus for iPad 2 2010-07-30 09:37 PM
can OF tasks show up in iCal (in the calendar not as tasks) msim iCal Sync 2 2008-02-12 06:33 PM
Quickly toggle between All tasks & Remaining tasks Ward OmniFocus 1 for Mac 2 2007-10-23 01:52 PM


All times are GMT -8. The time now is 11:39 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.