Hi everyone,
I have seen multiple forum posts with questions about leveling and units < 100%, but haven't found the answer I was looking for. I am using Omniplan 2.1.2.
My example:
- two tasks: Start (1d) and Finish (6d)
- resource group "my team" with John and Mary
- resources are set to "keep effort fixed"
- the team works part-time (50%)
- I assign the tasks to "my team"
To specify the resources are working part time, I have set their units to 50%.
They don't have fixed schedules, all I know is that they work 20 hours a week.
When I level my project, each task is done both by John (50% of 50%) and Mary (50% of 50%).
This is not what I expect. I would expect only one person to work on the task, and automatically adjust the duration if necessary.
Any suggestions?
I have seen multiple forum posts with questions about leveling and units < 100%, but haven't found the answer I was looking for. I am using Omniplan 2.1.2.
My example:
- two tasks: Start (1d) and Finish (6d)
- resource group "my team" with John and Mary
- resources are set to "keep effort fixed"
- the team works part-time (50%)
- I assign the tasks to "my team"
To specify the resources are working part time, I have set their units to 50%.
They don't have fixed schedules, all I know is that they work 20 hours a week.
When I level my project, each task is done both by John (50% of 50%) and Mary (50% of 50%).
This is not what I expect. I would expect only one person to work on the task, and automatically adjust the duration if necessary.
Any suggestions?