Inability to adjust for tasks that are completed ahead of schedule Thread Tools Search this Thread Display Modes
I have exactly the same problem as this one, which is the inability to adjust for tasks that are completed ahead of schedule, meaning if i have three tasks:

A, B, C , and im doing task A right now:

A
....B
........C


but if B is done ahead of schedule, when leveling, it ought to look like this :

A
....B
....C

instead of not changing at all


looks to me like its not differentiating between completed tasks and uncompleted ones, Thanks in Advance.

Last edited by mr_projects; 2007-10-30 at 10:25 AM..
 
That does sound like incorrect behavior. If task B is completed, and task C was delayed because it uses the same resource as task B, then it should be moved earlier. Oh, unless there's a dependency between task B and task C. If that's the case, you'll need to enter task B's actual completion date before task C will adjust the way you'd expect.

If you're still seeing something that smells like a bug, feel free to send an email to our ninjas at omniplan@omnigroup.com
 
I'd like to show an example, as well as the attached file

all tasks are attached together with F->S links, in this example B is 100% complete ahead of schedule, when leveling, it doesn't adjust C accordingly. I hope you got my point
Attached Thumbnails
Click image for larger version

Name:	Screenshot_1_620x400.shkl.jpg
Views:	876
Size:	10.5 KB
ID:	356  
Attached Files
File Type: zip example.zip (2.2 KB, 827 views)
 
Quote:
Originally Posted by mr_projects View Post
I'd like to show an example, as well as the attached file

all tasks are attached together with F->S links, in this example B is 100% complete ahead of schedule, when leveling, it doesn't adjust C accordingly. I hope you got my point
In this situation, we'd recommend setting the end date of Task B to when it was completed. With the dependency connection between Task B and C, Task C won't start right after Task A because it has to start right after Task B's "Finish to Start" connection.

If you remove the connection between Task B and Task C (provided that all tasks are assigned to the same resource), you'll see Task C being leveled to start right after Task A like you wanted it to.

So for now, you should either change the end date of Task B or remove the dependency connection between Task B and Task C. I've filed a feature request in our database for an easier way to mark a task completed "today" and to automatically set the end date to reflect that.
 
Im so thankful for your suppprt,

Im hoping there is a way to automatically remove the necessary dependencies when marking future tasks done

Thanks,
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can't Move / Adjust tasks - help! [A: Spotify, VLC, & Rdio for Mac interfere with the mouse] tonyg0192 OmniPlan General 12 2013-01-22 06:18 PM
How do you schedule tasks? J R Applying OmniFocus 9 2010-06-05 05:34 AM
Adjust actual for being ahead of schedule jwhitley OmniPlan General 6 2007-10-11 02:21 PM
Inability to Sync iCal Tasks w/out Context supafly iCal Sync 1 2007-08-19 07:19 AM


All times are GMT -8. The time now is 04:04 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.