Hi,

I added a few calendar exceptions for some staff in my work calendar. When leveling the project OP still attempts to allocate to the resources during the exception periods. Am I doing something wrong?

Rob
 
That does sound like maybe you're not doing what you think you're doing. Could you send us the file so we can take a look? (Help > Send Feedback will offer to attach a copy of the file with all the task names turned into things like "Task 1" if your data is particularly sensitive.)
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Leveling ignores completed tasks jelliot OmniPlan General 6 2011-09-08 02:51 PM
OmniOutliner import ignores dependencies michaelaye OmniPlan Extras 0 2011-05-18 02:14 PM
Financial contingency within resource leveling Kendall OmniPlan General 1 2010-05-20 03:24 PM
Leveling ignores completion status? frankrei OmniPlan General 8 2008-10-14 04:05 PM