I'm trying to create a hammock task. In attempting to recreate the tutorial (glue; let glue dry; spray top coat), I've set a "let glue dry" effort of 3H. After creating the dependencies the way I *think* they're supposed to be, and then turning the "let glue dry" task into a hammock, it's duration is reduced to .25H (or whatever effort I set the "spray top coat" task to. In the attached .png, I have no resource attached to the hammock task, but even when I assigned it to a resource "factory", the results are the same. Perhaps my dependencies are wrong.

The attached PNG is how things look just prior to to changing the task 2 to a hammock task.
Attached Thumbnails
Click image for larger version

Name:	Pre_hammock.png
Views:	654
Size:	39.0 KB
ID:	2492  

Last edited by omnibob; 2012-08-14 at 07:59 AM..
 
Omni explained to me that I just need to set the start date/time of task 3 to wherever is needed, to adjust the length of the hammock. Problem solved.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to use hammock task for client feedback? jefvdv OmniPlan General 1 2013-04-11 02:46 PM
Resource effort per task andrey44 OmniPlan General 0 2012-11-26 07:21 AM
Zero effort task charlax OmniPlan General 2 2012-03-02 04:01 PM


All times are GMT -8. The time now is 12:08 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.