Resources vs. Effort Redux Thread Tools Search this Thread Display Modes
3 resources are assigned to complete a task with a total time of 26 hours.

Do I have to add 3 resources and separate them out (2x8 hours + 1 x 10 hours)?

All 3 resources do the same job each week.

Thanks
 
Yes, you'll probably want to have a separate resource for each person, with their own schedules.

In addition to their differing work days, you'll be able to handle situations were one person needs a particular day off. That way, you can use the calendar view to update their availability independently from the other two folks' and still have the plan work out accurately.

Hope this helps!
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed Cost, Fixed Duration, Flexible Effort/Resources metasim OmniPlan General 2 2012-02-03 04:24 PM
Effort adjustor KlassicJazz OmniPlan General 0 2011-01-09 08:06 AM
jungledisk redux kingsinger OmniFocus Syncing 0 2008-08-28 01:37 PM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM
effort/duration toddbg OmniPlan General 1 2006-09-05 11:05 AM


All times are GMT -8. The time now is 04:01 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.