The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Today's Posts

 
Probably a Dumb Question Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I'm transferring over information from Smart Sheet to OP (a real project mgmt program) and have a quick question.

When we created our list of tasks, we simply assigned "end dates" to each one. Is there a way to set them up in OP that way instead of duration?

I tried putting them in the inspector but the dates show up under "constraint end date" and the item doesn't change on the gantt chart.

Any help is always appreciated - thanks!

Chris
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Another dumb question lsamberg OmniPlan General 0 2011-11-02 10:38 AM
Okay, I need to dumb this down. How do you do this in MobileMe? dcwinton iDisk/MobileMe/.Mac Syncing 1 2008-07-13 01:40 PM
Something Dumb I'm doing - quickentry window question filmgeek OmniFocus 1 for Mac 3 2007-10-09 07:48 PM
Help: Web export "broken" ? or am I dumb Minime2 OmniPlan General 3 2007-03-19 02:32 PM


All times are GMT -8. The time now is 10:04 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.