Is there a way within OmniPlan to generate reports, either from within the program or programmatically? The data I am after in particular is the amount of hours a particular resource is scheduled for by month going forward.

Any ideas about how to about getting to this?
 
To follow-up on this, I am after the monthly scheduled hours per resource to inform hiring and staffing decisions. I've planned out all of our tasks, assigned them to resources, leveled, etc. In the resource view I can see where the pain points are in terms of resource load (red bars), but I am not exactly clear as to what over 100% of the resource load means. Does over 100% mean 5 hours over for that week or are 100 hours scheduled for that particular resource? I have no idea how to find this out.

Any ideas?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
iCal reporting iangall OmniPlan General 0 2009-09-18 03:59 PM
Changing date from month/day/year to day/month/year RickM OmniPlan General 2 2009-01-27 09:06 AM
Reporting?? signal15 OmniFocus 1 for Mac 5 2008-09-26 12:14 PM
Due Soon not reporting Smhearty OmniFocus for iPhone 2 2008-07-21 01:26 AM
Reporting... loungeapple OmniPlan General 1 2007-03-05 01:03 PM


All times are GMT -8. The time now is 12:34 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.