In my project plans, I often need to allow a customer some number of days to review a deliverable. The review may take 2 hours, but we often need to allow them three working days to accomplish it. How do I set effort and duration to account for this, so that:

* the effort comes out right in reports (2 hours)
* we allow three days for its completion, and
* if the task is actually completed in 1 day, our revised project plan can account for that?
 
You could create a 2 hour long task and set a start and end date constraint in the "Task : Information" inspector. This allows you to note that the task will only take 2 hours, but it can be done within that 3 day time frame. If the task actually takes 1 day instead of 2 hours, you would just adjust the effort value to 1 day.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Duration not to be connected to working hours lorew OmniPlan General 3 2011-10-11 10:07 AM
Exporting Duration/Effort To CSV dmabram OmniPlan General 0 2008-03-10 09:32 AM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM
effort/duration toddbg OmniPlan General 1 2006-09-05 11:05 AM


All times are GMT -8. The time now is 12:20 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.