Since I upgraded to Omniplan v2 i've encountered a problem that I can't get to the bottom of.
I've created a brand new plan, and want to retrospectively enter project tasks from November into the plan, so i've set the start date for the appropriate date. I've also entered a load of tasks, but with no dependencies, resources assigned or any other detail.
For some reason there are a number of tasks that I can't set the dates to before today's date, however this is only the case for some of the tasks.
Anyone else had this problem? Am I missing something? Why are some of the tasks restricted to today's date? How can I remove this restriction?
If this was due to any dependencies or constraints i'd understand, but this is a brand new plan!
Help!
Since I upgraded to Omniplan v2 i've encountered a problem that I can't get to the bottom of.
I've created a brand new plan, and want to retrospectively enter project tasks from November into the plan, so i've set the start date for the appropriate date. I've also entered a load of tasks, but with no dependencies, resources assigned or any other detail.
For some reason there are a number of tasks that I can't set the dates to before today's date, however this is only the case for some of the tasks.
Anyone else had this problem? Am I missing something? Why are some of the tasks restricted to today's date? How can I remove this restriction?
If this was due to any dependencies or constraints i'd understand, but this is a brand new plan!
Help!