Hi, I am a new user of OMNIPLAN, I did created a schedule, however this was moved a few weeks forward and I need to ask how t move all tasks two weeks forward instead of moving every task?
 
In the Project: Information inspector, available with cmd-4 or the Inspectors menu, there is a spot where you fill in the start date of the project. Change that, and all the dates in your project will adjust accordingly, if you have constructed your project properly.

When I say properly, I mean that you have defined the structure of your project with dependencies, lead times, etc. rather than manually typing in dates or dragging items on the Gantt chart. Usually, only external factors require you to set actual dates, and those external factors are likely to remain unchanged even though you are starting your project a little earlier or later. If your project is to build a new Thunderbolt disk enclosure, the date on which Intel can provide you with the needed chips won't change just because you start your design work a little earlier, so that's a good thing to enter with a date. If on the other hand, you had put in a date to show that your PC board vendor wouldn't have completed PCBs for you to stuff until 72 hours after you submitted the design files, that would be an improper use of a date in my opinion, and you should use a lead time instead, because that should move around with any changes made in the plan that changed the date on which the PCB vendor got the design files.

Clear as mud?
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
What have I got on 6 weeks from now? Kexwolf Applying OmniFocus 4 2010-12-27 04:25 AM
Counting weeks juliabell OmniPlan General 2 2010-05-06 02:57 PM
Header went from days to weeks jjdoyon1 OmniPlan General 1 2010-02-15 08:05 PM
Ability to show time in "in three weeks, in two weeks, tomorrow" formats mr_projects OmniPlan General 1 2007-11-02 11:28 AM


All times are GMT -8. The time now is 04:09 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.