I have a resource assigned to 6:30 pm to 9:30 pm schedule and another one with the same availability.

One task that requires both will take 3 hrs to complete, another will take 2 hrs.

However, OmniPlan is scheduling the tasks for mid-afternoon starting at 2:30.

This makes no sense. I've double checked assignments and schedules and re-leveled.

Any ideas? Thanks in advance!
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Backdating completed tasks (esp. after rescheduling/leveling) omnibob OmniPlan General 1 2013-02-08 09:34 PM
Difficulty Splitting Tasks During Leveling morricej OmniPlan General 4 2012-02-14 07:53 AM
Leveling ignores completed tasks jelliot OmniPlan General 6 2011-09-08 03:51 PM
Issues with leveling constrained tasks bjamison@exacttarget.com OmniPlan General 1 2007-11-09 05:30 PM
Leveling of short duration tasks bgeipel OmniPlan General 3 2007-11-09 09:58 AM


All times are GMT -8. The time now is 12:17 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.