I'd like to set up a task that doesn't have a duration or an effort, but instead is bounded at the beginning and at the end by dependencies on other tasks.

As an example, let's say I have a QA Testing task - it should start a little while after the start of Software Construction, and it should continue for as long as Software Construction (which is a group task) goes on.

Is this possible? Is so, how?

Thanks in advance,
Scott
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
End Constraints matthewforsyth OmniPlan for iPad 1 2013-04-01 05:28 PM
Actual and Constraints tonygoulding OmniPlan General 0 2012-08-22 04:31 AM
How to require multiple resources at the same time? elj OmniPlan General 1 2012-03-27 11:33 AM
Multiple Constraints? bwilder1998 OmniPlan General 1 2012-03-08 12:02 PM
Constraints rroskelley OmniPlan General 8 2008-12-08 09:59 PM