How to suppress idle days in gantt view? Thread Tools Search this Thread Display Modes
I'd like to suppress idle days (i.e. days on which nothing happens) in the gantt view (and subsequent pdf-export for sending to non OP-users). Filtering seems not to help or is inefficient to the least, as I would have to enter exact dates to filter idle days out. Any ideas?

Be.
 
You can edit the project's work schedule to remove those idle days, which will suppress them from being displayed. This is a bit dangerous if those idle days might turn into non-idle days, as OP won't be scheduling any activities on those days even if it might now be otherwise possible. On the other hand, if you just need to do this on occasion to provide a document to someone else, you could just duplicate the project file, strip out the idle days, make your document, and never alter the original project file.

Send in your request for a feature to automatically hide days with no work planned with Help->Send Feedback or email omniplan@omnigroup.com.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can I show holidays in Gantt view? ajrichardson OmniPlan General 2 2009-11-28 06:36 PM
Gantt - day divisions in month view christobaldo OmniPlan General 1 2009-01-21 03:28 PM
Cumulative Days in Gantt Chart danielgjohnston OmniPlan General 3 2007-08-21 02:29 PM


All times are GMT -8. The time now is 02:21 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.