I'm transferring over information from Smart Sheet to OP (a real project mgmt program) and have a quick question.

When we created our list of tasks, we simply assigned "end dates" to each one. Is there a way to set them up in OP that way instead of duration?

I tried putting them in the inspector but the dates show up under "constraint end date" and the item doesn't change on the gantt chart.

Any help is always appreciated - thanks!

Chris
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Another dumb question lsamberg OmniPlan General 0 2011-11-02 11:38 AM
Okay, I need to dumb this down. How do you do this in MobileMe? dcwinton iDisk/MobileMe/.Mac Syncing 1 2008-07-13 02:40 PM
Something Dumb I'm doing - quickentry window question filmgeek OmniFocus 1 for Mac 3 2007-10-09 08:48 PM
Help: Web export "broken" ? or am I dumb Minime2 OmniPlan General 3 2007-03-19 03:32 PM


All times are GMT -8. The time now is 07:33 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.