The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
effort/duration Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I started a new project and broke out my tasks,
in looking at the column for effort and the other for duration they do not match.

since I have an 7hour working day with a task that is 7h in effort - should not the duration also equal 1 day rather than 1d 4 h?

Thanks
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Decouple Effort and Duration? highcamp OmniPlan General 35 2013-03-15 05:13 PM
unlinking effort & duration thormar OmniPlan General 3 2011-07-29 04:07 PM
Different units for duration and effort? LJRolf OmniPlan General 3 2011-02-07 11:39 AM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 05:50 PM


All times are GMT -8. The time now is 03:41 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.