I just started using OF and I'm loving it so far. I love that it seems streamlined yet flexible. Great job.
Something I noticed a need for as I've set up my extensive project list... dependent actions. I love that a project can be set up to be either serial or parallel in terms of when a task becomes available. I find that, for most of my projects, I have a mid-sized list of actions. Most of these actions can be started right away but occasionally an action is dependent on one other task. I know that I could manage this with subprojects even when I have large projects with subprojects I'm running into a need for sub sub projects to handle this. For now, I'm just putting some of these one off dependent tasks in a waiting for context and then updating the context during a daily review when the task they were dependent on was completed.
Shanana
Something I noticed a need for as I've set up my extensive project list... dependent actions. I love that a project can be set up to be either serial or parallel in terms of when a task becomes available. I find that, for most of my projects, I have a mid-sized list of actions. Most of these actions can be started right away but occasionally an action is dependent on one other task. I know that I could manage this with subprojects even when I have large projects with subprojects I'm running into a need for sub sub projects to handle this. For now, I'm just putting some of these one off dependent tasks in a waiting for context and then updating the context during a daily review when the task they were dependent on was completed.
Shanana