Omit items from critical path? Thread Tools Search this Thread Display Modes
I'm working on a plan that has some external time constraints, and I wanted to represent those as milestones and groups of milestones. One of the goals is to complete the project before the last milestone.

Is it possible to set the critical path so that it omits those time constraints? Right now, the latest date in my plan is a milestone out past the end of all the other items, and as a result, it's a one-item critical path.

I can view the real critical path by deleting the external time constraint tasks, but I wonder if there's another way to handle it.

Thanks in advance,
Scott
 
Quote:
Originally Posted by sshorter View Post
I'm working on a plan that has some external time constraints, and I wanted to represent those as milestones and groups of milestones. One of the goals is to complete the project before the last milestone.

Is it possible to set the critical path so that it omits those time constraints? Right now, the latest date in my plan is a milestone out past the end of all the other items, and as a result, it's a one-item critical path.

I can view the real critical path by deleting the external time constraint tasks, but I wonder if there's another way to handle it.

Thanks in advance,
Scott
There isn't a way to omit/hide anything from the critical path in OmniPlan. Your method of removing the external time constraint tasks is probably the best way to handle this currently.

We may implement some kind of hiding/omit feature in a later version of OmniPlan, but I don't know how leveling would behave with that feature. I'll make a note of this in our database for you. :-)
 
i would vote for this feature 0 regularly lie to have external milestones ina group and it messes up ciritical path analysis
 
Your vote has been added. :-)
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical Path - won't highlight path aboeing OmniPlan General 4 2014-04-09 12:49 PM
Set a different text style for critical path items? sabeke OmniPlan General 3 2009-06-11 05:12 PM
Critical Path MacBerry OmniPlan General 11 2009-03-15 07:36 AM
Critical path coloring BSteely OmniPlan General 1 2007-04-09 11:21 AM


All times are GMT -8. The time now is 05:42 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.