I have a bunch of tasks that I want to start as soon as possible, then they all need to wait until after a dependency finishes, then they have another 3 days of effort left.
Any ideas how to plan for this up front? I know how to split tasks, but how do I get the first part to start ASAP (no dependencies) and the second part to start after the dependency finishes and take 3 more days?
One of the reasons I don't want to show it as two separate tasks linked with a dependency is that I want to assign the resource from a pool of 4 developers and I want the program to auto level. Of course the same developer needs to work on both parts of the task.
Thanks,
Mike
Any ideas how to plan for this up front? I know how to split tasks, but how do I get the first part to start ASAP (no dependencies) and the second part to start after the dependency finishes and take 3 more days?
One of the reasons I don't want to show it as two separate tasks linked with a dependency is that I want to assign the resource from a pool of 4 developers and I want the program to auto level. Of course the same developer needs to work on both parts of the task.
Thanks,
Mike