I've noticed that any task groups or " sub projects " are automatically sequential ? The tasks below the next action are all grayed out .
It appears this can't be changed by the inspector because it's following the preference of the " parent " project ?
 
You can change an action group from sequential to parallel by right-clicking on it and selecting parallel from the context menu that pops up. This is not the ideal interface (as has already been discussed in another thread), but I would expect Omni to clean it up before the final release of OF.
 
oh that's cool . I missed that somehow .. works for me !

thanks again : )
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Task groups, and sequential work omnibob OmniPlan General 2 2012-02-10 04:30 PM
Parallel vs Sequential Action Groups masoric OmniFocus for iPad 2 2010-10-02 07:47 AM
Action Groups Don't Get Marked as Done Automatically minato2 OmniFocus for iPhone 15 2008-11-25 01:39 PM
Shouldn't task get automatically moved to projects? tango OmniFocus 1 for Mac 8 2007-07-29 04:05 AM
should projects (and task groups) be parallel by default? markbrown00 OmniFocus 1 for Mac 10 2007-07-09 01:17 PM