I have a group of sequential events that I want to repeat every month.
For this month, I have them set with with a start date of 4/1 and "repeat every 1 month". When I complete the 1st task in the group, next month's copy spawns immediately below it (blocking the next task in the sequence) rather than at the end of the list. Is there a way to accomplish this?