Hi,

When I flag the checkbox in the leveling menu : Don't schedule any task before date : 09/09/11 - which is tomorrow in this case. Omniplan does level some tasks to start BEFORE the 9th of September. He schedules them even to the 7th of September (which was yesterday in this case). How can this be ?
I am doing something wrong ?

Please advise,
 
Only non-completed work is rescheduled. If you have a partially completed task, the task will move such that then incomplete work can be resumed at a time that efficiently utilizes your resources. If a task is fully completed it won't move at all.

If that doesn't explain the issue, please send a redacted version of your document to the support ninjas via the Help -> Send Feedback menu item.

-Tom
 
Hi Tom,

Thank's for your reply, but I have this issue with 2 both non completed tasks (not even partially completed). I'll send a version of the document.
-Luke
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
leveling priorities luke18 OmniPlan General 2 2011-09-28 12:36 AM
Leveling resources connie OmniPlan General 1 2006-08-22 05:10 PM
Priority in leveling DeanC OmniPlan General 2 2006-08-15 02:27 PM


All times are GMT -8. The time now is 09:55 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.