The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
How to suppress idle days in gantt view? Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I'd like to suppress idle days (i.e. days on which nothing happens) in the gantt view (and subsequent pdf-export for sending to non OP-users). Filtering seems not to help or is inefficient to the least, as I would have to enter exact dates to filter idle days out. Any ideas?

Be.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can I show holidays in Gantt view? ajrichardson OmniPlan General 2 2009-11-28 06:36 PM
Gantt - day divisions in month view christobaldo OmniPlan General 1 2009-01-21 03:28 PM
Cumulative Days in Gantt Chart danielgjohnston OmniPlan General 3 2007-08-21 02:29 PM


All times are GMT -8. The time now is 05:26 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.