Is it possible to set people as fixed resources on a task in such a way that OmniPlan will require all the assigned resources to be available for the task?

I have a series of operational tasks during a project (such as code deployments) that require all of the assigned staff to be present for the task. OmniPlan keeps scheduling these tasks during the vacation of one or more resources because it figures the other assigned resources can pick up the slack.

I'd like to be able to tell OmniPlan that a task is a specific duration (which I can do) and that all resources must be present for the full duration. Can I do that?
 
 