Task splitting is being worked on right now for OmniPlan 2.0. Thanks for all the votes everybody!
Post 21
|
Guest
2009-04-30, 12:08 PM
The corollary to this is being able to assign a staff resource by amount (e.g. 40 hours of Tim) rather than a continuous level of effort. make sense?
Post 22
|
Guest
2009-10-18, 09:27 AM
Hi!
Please add my vote too (if that's any use now that it's being worked on..) I have a question regarding the planned implementation. I never used Microsoft Project so I don't know how task splitting works ... but what I'd like is the leveling function to be intelligent enough to optimize 2 overlapping tasks as such, when needed (ex : especially if some other tasks are depending on task2 to start) : task1 : --------------- task2 : -- result: 11112211111 is this the way it will work ? thanks!
Post 23
|
Member
2009-11-25, 04:41 AM
Registered just to say thank you for working on this feature as this will certainly improve the usefulness and accuracy of my planning. Keep up the great work!
Post 24
|
Member
2009-12-15, 09:28 PM
Me too!
Post 25
|
Member
2010-01-04, 06:22 AM
I just figured out that this feature was not in Omniplan, which makes it almost useless for my needs. Just to clarify, I need to be able to assign actual hours against an actual task for an individual so that it reflects what they were working on that week. Guess I'm going to have to import the project into MS Project for now. Yuck! I am relatively experienced with MS Project and it really sucks!
Post 26
|
Member
2010-02-02, 07:32 AM
+1
Thanks...
Post 27
|
Post 28
|
Member
2011-04-09, 10:11 PM
Post 29
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
repeating projects/tasks when all tasks/subtasks are complete? | djc225 | OmniFocus 1 for Mac | 1 | 2012-03-20 06:55 PM |
Mirroring tasks/Changing color of flagged tasks | OmniFocused | OmniFocus 1 for Mac | 3 | 2011-09-21 04:20 PM |
Adding tasks in inbox on iPad deletes other tasks | kocab | OmniFocus for iPad | 2 | 2010-07-30 09:37 PM |
can OF tasks show up in iCal (in the calendar not as tasks) | msim | iCal Sync | 2 | 2008-02-12 06:33 PM |
Quickly toggle between All tasks & Remaining tasks | Ward | OmniFocus 1 for Mac | 2 | 2007-10-23 01:52 PM |