Hi All,
I've got a task that has a single person assigned at 100% of 100% for 3 days. The normal work schedule is 9AM-Noon, 1PM - 6 PM. When I set up the task with the start and end dates using the default daily schedule, Omniplan gives me anywhere from 15 - 45 minutes extra on the duration. When i set the duration to 3 days, it fiddles the end time for the task.
I'm not sure what's going on or why, so any explanations would be appreciated.
Charles
I've got a task that has a single person assigned at 100% of 100% for 3 days. The normal work schedule is 9AM-Noon, 1PM - 6 PM. When I set up the task with the start and end dates using the default daily schedule, Omniplan gives me anywhere from 15 - 45 minutes extra on the duration. When i set the duration to 3 days, it fiddles the end time for the task.