Durations / End date/times weirdness Thread Tools Search this Thread Display Modes
Hi All,

I've got a task that has a single person assigned at 100% of 100% for 3 days. The normal work schedule is 9AM-Noon, 1PM - 6 PM. When I set up the task with the start and end dates using the default daily schedule, Omniplan gives me anywhere from 15 - 45 minutes extra on the duration. When i set the duration to 3 days, it fiddles the end time for the task.

I'm not sure what's going on or why, so any explanations would be appreciated.

Charles
 
It's usually hard to tell exactly what is going on from a verbal description and no idea of the context. I would suggest you use Help->Send Feedback in the app to send a sanitized copy of your document to the support ninjas (tell them the task ID of the offending task, because the text will just be Task 1, Task 2, etc.)

What is your scheduling granularity, and how are you setting the start and end times of this particular task? Have you changed the efficiency of the resource you've assigned?
 
I'm also seeing efforts displayed as fractions of days. My tasks start on day one at 8 am and end on day X at 5 (which is what my work calendar considers an entire day: 8-5). However, I end up with efforts that are fractional. I've been able to edit some manually, others seem linked to other fractional tasks and changing one just cascades into the next.

All tasks are set to begin as early as constraints allow. Which, strangely, seems to reset at times to begin on a set date. Different thread.

I can provide more detail. But help would be appreciated.
 
Again, same suggestion. You can also make an anonymized copy of your document by going through the Help->Send Feedback route and saving a copy of the attachment to your desktop before (or instead of) sending it. Zip it up and attach it to a post here and I'll take a look at it, maybe the support ninjas are backed up right now...
 
I can't find the anonymized file on my system. The Feedback dialog says it's going to have a name consisting of part of my email address and date. Can't find it w/ Searchlight. Any thoughts?
 
Once you've got the message composed, simply drag the attachment to the desktop.
 
I didn't get any formatted email from which to drag/save an attachment. I'm assuming OP uses Mail, but I haven't configured it. Using Outlook. Any other way to generate a gibberish-y doc?

Thx.
 
Yeah, it uses Mail. I think if you go through the Mail configuration process it will offer to create you a 60-day free trial MobileMe account, or you could go sign up for a gmail account, or some other free POP or IMAP account. You'll make your experience getting support from Omni much easier if you have at least one account set up in Mail, assuming you aren't willing to send them a straight copy of your document.

If you can't or won't do that, make a copy of your document, then open it in OmniPlan as the only window. Open the Applescript Editor application, and paste in the following code:

Code:
tell application "OmniPlan"
	repeat with _task in tasks of front document
		set name of _task to "Task " & id of _task
		set note of _task to "xxx"
	end repeat
	repeat with _resource in resources of front document
		set name of _resource to "Resource " & id of _resource
		set note of _resource to "xxx"
	end repeat
end tell
Execute the script and your document should be made safe for public consumption, though you should have a look to make sure of that. Save the file, zip it up and attach to a posting or email to omniplan@omnigroup.com. Be sure to identify the spot which is giving you trouble!
 
Thanks for the trick! Yeah, don't want to configure Mail on my work Mac. I've had some Exchange weirdness and don't want to get into issues of whether something is or is not on the server blah blah blah.

File attached. Pretty simple, actually. Nonetheless, take a look at tasks 402 or 246, for example. In fact, anything that isn't rounded to a full day is problematic for me in the way I'm trying to track projects. I've checked the start and end times and they map to the project calendar. I've attempted to delete assignments to resources and/or set all resources to 100% to see if that would undo things -- no luck. Hoping there's some low-level setting I haven't identified. Checked the project-level granularity and that's set for full days.

It's not really a big deal at the level of detail and complexity I'm working at now but I'm trying to build a consistent schedule platform that I can confidently add detail to. At some point (e.g. when Duration and Effort are separated...) these minor differences may begin to add up to problems which is why I'd like to solve them now.

Thanks again for all the help.
 
Uh, except there's no file attached to your post... maybe you forgot to click the Upload File button after selecting it?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Lead times before locked task e.g. ordering pre fixed delivery date marcd OmniPlan General 10 2009-09-03 06:54 PM
Perspective weirdness Chris OmniFocus 1 for Mac 1 2008-01-08 12:49 PM
remove times in start and due date creativityist OmniFocus 1 for Mac 18 2007-12-15 12:58 PM
Print as PDF weirdness jmckeown OmniWeb General 1 2007-05-22 09:45 AM
OW encoding weirdness with MT Gregory OmniWeb Bug Reports 0 2006-11-17 07:38 PM


All times are GMT -8. The time now is 11:24 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.