Request: constrain to specified work week Thread Tools Search this Thread Display Modes
I seem to be full of requests this week, yet another one comes up while working.

When working with a template of unspecified start date:

You duplicate the template and give it a name, then give it a start date. Even with a Monday-Friday workweek, it will take a weekend start date, and as my project file is quite complex, I have not had a chance to fully check the schedule to see of the dates for each task are on a workday or not.

Is there a way to constrain the date you start, and those for individual task starts to the designated work week?

If not, can you provide a checkbox for this somewhere in the file, or perhaps make it the default, and then have a checkbox to turn the feature off?

Thanks!
 
Tasks will move to working days. If a task is set to start on a non-work day, then the task will be moved to the next work day. If that's not what you're seeing, please email support at omniplan@omnigroup.com with more specifics. Thanks.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Repeating Tasks on work week Callen OmniFocus for iPhone 4 2010-08-29 07:55 AM
FR: Tasks repeat/recur on work week schedule dbyler OmniFocus 1 for Mac 6 2010-08-28 08:11 AM
"Work Day Hours" and "Work Week Days" in General Preferences dhm2006 OmniFocus 1 for Mac 2 2007-09-05 01:50 PM
adjusting work week danwenke OmniPlan General 1 2007-07-09 04:39 PM