Hi everyone,

I am a relatively new user to Omnifocus, so I apologize if this is a common sense question, but I have not yet found the answer in the forums.

I recently input a significant number of new actions, many of which have due dates of this coming monday (2 days from now). All actions were associated with both Contexts and Projects.

When I view the "Due" menu at the top of Omnifocus, it shows three different Subcategories: "Due Today", Due Tomorrow", and "Due within the next week".

The issue is that the items listed within "Due within the next week" are incomplete. It is only showing actions from within one of my "Single-Action Lists". Why would Omnifocus prioritize those actions for the "Due" view?

Am I doing something wrong or missing something?

Thanks in advance for your help.

best,
Aaron
 
My guess is that you have entered these as sequential projects, and are viewing Available actions. With a sequential project, subsequent actions are not treated as Available if there is an action earlier in the project that is incomplete. With a Single Action List, or a parallel project, incomplete actions don't block subsequent ones from being Available, which would explain why you are only seeing the future items from your Single Action Lists.

If you change your view selector to show Remaining or All actions, I think the missing items will show up.
 
Quote:
Originally Posted by lazyline77 View Post
the items listed within "Due within the next week" are incomplete. It is only showing actions from within one of my "Single-Action Lists". Why would Omnifocus prioritize those actions for the "Due" view?
Quote:
Originally Posted by whpalmer4 View Post
My guess is that you have entered these as sequential projects, and are viewing Available actions.
In OF 1.8, using Where in OF, you could quickly check which projects are set as sequential by running the saveable search:
projects where sequential is true
Tasks flagged as sequential inside generally parallel projects could be listed with:
tasks where sequential is true and (sequential of its containing project is false)
and a simple listing of tasks due within the coming days could be generated by some variant of:
tasks where (due date ≥ today) and (due date ≤ (today + 6 * days))
--

Last edited by RobTrew; 2012-07-17 at 07:48 AM..
 
Thanks everyone.

I still haven't figured out what it was, but shortly after I made this post, OF synced itself and that seemed to make the missing items appear.

Still not sure exactly what that means, but I appreciate your help.

All the best,
Aaron
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Confused by "Normal Work Week for Project" behavior Jason Heath OmniPlan General 2 2011-03-13 05:55 PM
How to make a "What I did Today/This Week" report? [SOLVED: See thread, email ninjas] ralfloebelt OmniFocus 1 for Mac 8 2009-05-12 12:44 PM
Bug after removing everything from "Normal Work Week" schedule? mikar@mac.com OmniPlan General 0 2008-03-09 09:38 PM
"all day" option for the standard work week for the whole project mr_projects OmniPlan General 2 2007-11-02 12:53 PM
"Work Day Hours" and "Work Week Days" in General Preferences dhm2006 OmniFocus 1 for Mac 2 2007-09-05 01:50 PM


All times are GMT -8. The time now is 12:04 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.