Normally, when I start writing a plan, I put some rough durations in for all tasks and only then start assigning resources to them. OP seems to fix Effort and recalculate Duration by default, which means if I don't assign exactly one resource to a task things go horribly wrong.
Is there an option to set the default for all new tasks. Of course it's not difficult to select all and change their setting, but I always end up adding a new task and forgetting to change it...
Is there an option to set the default for all new tasks. Of course it's not difficult to select all and change their setting, but I always end up adding a new task and forgetting to change it...