I work in an office were the average work day is 7.75 hours, but when I enter this into the Project:Formatting pane in the inspector, it rounds my time up to 7.8 hours. Is there anyway to force OmniPlan to use the number I've entered?

Thanks!
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Newbie question on Unit Conversion/Duration/Effort kurisu OmniPlan General 1 2012-06-12 05:13 PM
Due within next week- actions not showing up [A: Time as well as date factors in.] dhunter OmniFocus 1 for Mac 2 2011-12-10 01:22 PM
What are Effort Conversion Factors? santra OmniPlan General 3 2009-01-05 11:12 AM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM


All times are GMT -8. The time now is 01:08 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.