OmniPlan is trying to guess what I'm thinking! Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Hi all,

I realize I'm probably not using the software in the manner that is anticipated. Here's my goal:

I want to enter a task that takes 4w. I want to show that, during these four weeks, two people (resources) each spend about 20% of their time on this task. So, I enter 4w as the task's duration, but when I start to assign resources, the software changes the task's duration! When I had decided the task would take 4w, I had already taken into account how much (20%) of their time people would spend on the task.

How can I configure the software to primarily accept a task's duration without modifying it as I assign people and percentages?

I still would like to be able to take advantage of OP's ability to show me how "busy" a person is in the Resource Allocation view, so I wouldn't like to lose the percentage of a resource that is being used, but I don't want the duration of a task to change dynamically.

I hope this makes sense. Many thanks for any help!
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Feature Request I guess? Baarogue OmniFocus for iPad 4 2013-10-24 01:57 AM
Guess the Day !!! vballas OmniFocus for iPad 54 2010-07-30 06:36 AM
i guess I don’t understand Layers rmathes OmniGraffle General 2 2007-01-07 10:18 AM


All times are GMT -8. The time now is 04:23 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2021, vBulletin Solutions, Inc.